In July 2020 the government published Gear Change: a bold vision for cycling and walking which set out to do precisely that, to make cycling “the natural first choice for many journeys” by ensuring that any new cycle infrastructure is accessible to everyone “from 8 to 80 and beyond”.
Specifically it committed to building thousands of miles of new protected bike lanes:
“The routes must be direct. They must be continuous, not giving up at the difficult places. They must serve the places people actually want to go – often major public transport corridors – and the journeys they actually want to make. If it is necessary to reallocate roadspace from parking or motoring to achieve this, it should be done.”
LTN 1/20
New design guidance known as Local Transport Note LTN 1/20: Cycle Infrastructure Design (LTN 1/20) that local authorities must follow when making any changes to the highway – including new highway construction and new or improved cycle facilities – was published at the same time.
With immediate effect on 27 July 2020 the older design guidance contained in LTN 2/08 and LTN 1/12 was withdrawn, to be replaced with LTN 1/20.
Only councils whose schemes comply with LTN 1/20 will receive funding:
“These higher standards will make clear that schemes which consist mainly of paint, which make pedestrians and cyclists share the same space, or which do not make meaningful change to the status quo on the road, will not be funded.”
Active Travel England inspectorate
Gear Change announced that the updated design standards would be overseen by a new inspectorate called Active Travel England – which will perform a similar role to Ofsted – and will be responsible for the cycling budget and ensure schemes are compliant with the new standards.
There has been a delay in setting up the inspectorate but an announcement, including naming the new walking and cycling commissioner, is expected shortly. (edit 22nd January – it has now finally been launched with Chris Boardman overseeing the new body as the national walking and cycling commissioner).
Active Travel England will examine all applications for funding and refuse any that are not compliant with the new national standards:
“It will inspect finished schemes and ask for funds to be returned for any which have not been completed as promised.”
Active Travel Fund schemes
The Active Travel Fund was set up by the government to support local transport authorities with producing cycling and walking facilities. The funding was in two tranches:
- Tranche 1 supported the installation of temporary projects during the early stages of the COVID-19 pandemic
- Tranche 2 supported the creation of longer-term projects
Norfolk County Council was allocated £1.5m under tranche 2. The funding was awarded in November 2020.
Three schemes for Norwich were included in the bid:
- Ipswich Road – provision of mandatory cycle lanes on both sides of the carriageway between the Daniels Road junction and the St Stephens Road junction
- Heartsease Lane – provision of mandatory cycle lanes on both sides of the carriageway between Rider Haggard Road and the Plumstead Road roundabout, together with an upgraded crossing at Rider Haggard Road
- Mile Cross Road – provision of mandatory cycle lanes on both sides of the carriageway between Aylsham Road and Havers Road
Two of the schemes have gone out to consultation, both of which have been significantly reduced in scope.
When the Ipswich Road scheme went out to consultation in August 2021 it included segregated cycle lanes, as promised in the bid. However, when the scheme was presented to the Transport for Norwich committee for approval in January 2022 a second option was included which takes out almost half of the inbound cycle lane. Concerns from a nearby school about loss of car parking for parents dropping off children was the reason given for the change. The second option was the one approved by the committee. Voting was split 4/4. The committee chair Martin Wilby cast the deciding vote.
When the Heartsease Lane scheme went out to consultation in November 2021 the cycle lanes were removed altogether from the proposals. The scheme now consists of just the crossing upgrade. Again, a reluctance by councillors to remove car parking was cited as the reason.
In each of these cases what will be built on the ground will not match what was promised in the bid.
Transforming Cities Fund schemes
The Transforming Cities Fund was set up by the government to provide investment in public and sustainable transport infrastructure in English cities.
The money was allocated in two tranches. Tranche 2 had a particular focus on “local public and sustainable transport connectivity, improved access to jobs, reduced congestion and improved air quality”.
Norwich was awarded £32m under tranche 2, in addition to the £6m it had already received under tranche 1. An initial bid was submitted in November 2019 with a revised bid being submitted in May 2020. The award was announced in September 2020.

The bid included a wide range of projects that improve transport infrastructure for bus users, cyclists and pedestrians.
Significant cycling schemes for Norwich which have already been completed include:
- Prince of Wales Road
- Tombland
- Grapes Hill roundabout
Gear Change makes it clear that LTN 1/20 also applies to Transforming Cities Fund schemes:
“We will not allow any other agency or body to fund such schemes using any of our money. This includes schemes delivered through pots such as the Transforming Cities Fund.”
The Prince of Wales Road scheme was completed in early 2020 before LTN 1/20 was published and although the Tombland scheme was completed post-LTN 1/20 the plans were approved prior to its publication. Poor as these schemes are for cycling, we obviously can’t expect them to be LTN 1/20 compliant.
However, for schemes being implemented after LTN 1/20 was published there is a recognition that they should be designed to the currently applicable standards. A review document of the Transforming Cities Fund commissioned in 2021 by the Department for Transport talks of the “emerging challenges” of needing to “re-engineer schemes and re-skill engineers in light of Gear Change and new LTN1/20 cycling design guidance”.
The Grapes Hill roundabout scheme for instance went out to consultation in March 2021 and was approved in June 2021. LTN 1/20 had been in force for nearly a year by then.

An in-depth review of the failings of the scheme can be read here but the critical issues of the scheme can be summarised as follows:
- The scheme by design prioritises motor traffic
- The roundabout is now more dangerous for cycling
- The mitigating routes for cyclists are longer, slower and shared with pedestrians
- There is a dangerous blind bend on the Earlham Road shared-use path
- There is a narrow pinch point by the crossing on the Convent Road shared-use path which is a busy pedestrian route
- The narrow refuge for the two-stage crossing on Convent Road discriminates against users of non-standard cycles
This scheme categorically fails to comply with LTN 1/20. The following key design principles were not adhered to:
- Cycle infrastructure should be accessible to everyone from 8 to 80 and beyond: it should be planned and designed for everyone (Principle 1)
- On urban streets cyclists must be physically separated from pedestrians and should not share space with pedestrians (Principle 2)
- Where cycle routes cross pavements, a physically segregated track should always be provided (Principle 2)
- At crossings and junctions, cyclists should not share the space used by pedestrians but should be provided with a separate parallel route (Principle 2)
- On roads with high volumes of motor traffic cyclists must have physical protection, both at junctions and on the stretches of road between them (Principle 3)
- Cycle infrastructure should be designed for significant numbers of cyclists, as well as for non-standard cycles (Principle 5)
- Routes must join together to create a holistic, connected network (Principle 8)
- Schemes must be legible and understandable (Principle 10)
- Schemes must provide direct, logical routes that are easy and comfortable to ride (Principles 18 & 19)

The updated pedestrian and cycle crossing where the Pink Pedalway crosses Chapelfield Road is the one element of the scheme that was done to a high standard and shows the level of quality that the rest of the scheme should have attained.
Gear Change: one year on
In its review document Gear Change: one year on published in July 2021 the government made it clear that when the Active Travel Fund money was allocated Gear Change (along with its accompanying design guidance LTN 1/20) was the “plan for how the money will be spent”.
The review highlighted the fact that the money provided in 2020/21 through the two tranches of the Active Travel Fund was “to reallocate road space and create dedicated routes for cycling and walking”.
The government reiterated their commitment to reducing funding to councils which do not take active travel seriously:
“An authority’s performance on active travel will help determine the wider funding allocations it receives, not just on active travel.”






English Highways have rejected LTN 1/20 in evidence given to to the Iquity into the A47 Dualling. This is despite their Licence which requires them to implement Government policies