The A47 dualling, what about cycling?

For the past year work has been underway building a new road for the A47 west of Norwich, running from Easton to North Tuddenham, where it will join a previously dualled section. What does all this mean for cycling? Maybe more that you thought, albeit a badly substandard and inadequate scheme. Derek Williams explains

The whole scheme with the cycle tracks shown in red – Image National Highways

You can download the full sized high resolution PDF engineering drawing from National Highways here. It’s a large document (12.9MB in size) which needs a powerful computer to view easily.

Thanks to a Freedom of Information request made by a follower of ours, we discovered that shared use cycle tracks are being included as part of the new A47 project. This FoI also supplied very detailed engineering drawings as approved for construction, which contained details not shown on the drawing above, including some differences.

There will a new cycle route (shown in red above) almost all the way from the western edge of Easton to beyond Wood Lane, the B1135 to Lenwade.

This is a significant development, opening up the countryside west of the city to cycling. It is, however, nowhere near the standard we have a right to expect. This project is being run by the central government agency, National Highways, and they have a set of published guidelines for cycle infrastructure known as LTN 1/20 which seem to have been totally ignored.

There are two important issues with the plan which aren’t apparent from the large drawing above but are shown on the more detailed drawings – the width of the path and what its running surface is made of. Sad to say that much of the route is only 2m wide – the absolute minimum is supposed to be 3m (other than when this isn’t possible to get around pinch points) and large sections are surfaced with crushed stone, in effect making it little more than a “trod”.

Who is this cycle route designed for? The people most likely to want to use it would be long distance cyclists riding in from as far as Dereham. These riders will be riding bikes capable of sustained speeds of 20mph or more. This path is of little use to them.

The Food Enterprise Park

The new Food Enterprise Park, isolated from the cycle track (shown in red) – Image FEP

Between Easton and Honingham is a massive new employment area under construction to the south of the new A47 called the Food Enterprise Park (FEP). This will employ around 3000 semi-skilled or unskilled workers, so will become a major destination for a large number of low paid workers. The FEP is under 2Km from both Easton and Honingham, so cycling would provide a cheap and obvious way for these employees to get to and from work.

A new “direct access road” shown on the image above will run from the local access road near the Honingham roundabout through the FEP and out onto Church Lane near Easton. South Norfolk Distict Council is the planning authority, but Norfolk County Council, as the highway authority, recognised the need for a cycle route and made it a condition for phase 2 of the development that provision for active travel must be provided. The Phase 2 planning document (item 15) says:

“Prior to the first use of the development hereby permitted, the off-site walking and cycling highway improvement works … shall be completed to the written satisfaction of the Local Planning Authority“.

Access to the FEP is not an intended function for the new A47 cycle track.

Local access road

There will also be a local access road connecting Easton via the FEP junction on the A47 to the Honingham roundabout, shown to the right of the new A47 in the image above. There is to be no cycle track or even a footpath along this road, and no way to get through the junction from the cycle track along the northern side of new A47 without mixing with traffic accessing the FEP, which will include HGVs. The southern roundabout of the junction is in a deep cutting, meaning a substantial climb out.

The local access road will not be a safe nor easy road to cycle on, it cannot be considered a viable cycle route and it is certainly not designed as such. This should be made clear with some kind of signage.

Access from the A47 cycle route to FEP will either be from Easton or the Honingham roundabout.

The new cycle track route description

West of Easton to the FEP junction

The new cycle route (shown in black on the following drawings) starts on the western edge of Easton at which point it crosses over the new A47 by way of a bridge. The big zig-zag on the northern side is a ramp to get down from the bridge. There is also a staircase providing a more direct connection to Church Lane for pedestrians.

The bridge has a good running surface, but while the width of the actual bridge isn’t stated, the ramps and path leading to it are only 2m wide. This is not wide enough for two cargo bikes to pass.

The pedestrian/cycle bridge connecting Easton to Church Lane and the cycle track west

The new local access road from Easton runs along the top of the River Tud valley, with the new A47 lower down along the valley side, so the cycle track approaches the bridge above the new A47, meaning there’s no ramp up. But once on the northern side it descends via the zig-zag ramp to meet Church Lane, now severed at the top of the hill by the new A47, taking cyclists who wish to travel west some distance east which they then have to double back from.

Here Church Lane descends further into the valley and it’s uncertain how the cycle route will deal with the height differences. It’s clear this bridge has been designed first and foremost to connect to Church Lane and the cycle route along the new A47 has been fitted in.

Church Lane leads into the Ringland valley, and will remain open to pedestrians and cyclists, providing a low traffic route on Ringland Road into the valley.

The pedestrian/cycle bridge at Easton, looking west – Image SWECO

The new cycle route then heads west on the north side of the A47 as a 3m wide crushed stone shared use track, it can hardly be called a proper cycle route surface.

From Easton to the FEP junction. Note the new local access road to the south of the new A47

The cycle track eventually reaches the FEP junction. As stated above this is not intended as a route for cyclists to reach the FEP.

Taverham Road also connects to the FEP junction on the northern roundabout. Cyclists will follow a new alignment of Taverham Road leading from the FEP junction for a short distance, using the road before turning left it so as to follow a truncated section of the old A47 towards Honingham. There are 2m wide paths here or varying quality, but they seem designed for pedestrians only.

Where the cycle route crosses Taverham Road

Taverham Road will be the only route across the Wensum valley between Longwater Lane and Wood Lane (the B1135) and connects directly to the FEP so is likely to become a major rat-run.

This could become a chaotic place, although the new section of road from the northern FEP roundabout will be two lanes wide, for the rest of its length Taverham Road is a very narrow country lane which is unsuitable for any serious level of traffic.

Taverham Road, connecting to the FEP junction. A new rat-run? – Image Google Street View

FEP junction to the Honingham roundabout

The cycle track continues west of the FEP junction as a 2m wide crushed stone shared use track – again, way below the design standards and little more than a trod. It then crosses the new A47 through an underpass (the width of the underpass tunnel isn’t stated). The cycle track then reaches the old A47 at the existing roundabout at the junction with the road to Honingham village. There will be an uncontrolled crossing of the old A47 here to enable cyclists to get to Norwich Road leading to the village without riding around the roundabout. There will be no cycle infrastructure along Norwich Road.

The cycle route from the FEP junction to Honingham

After Honingham

The cycle route carries on heading west on the northern side of the old A47 from the Honingham roundabout as a 2m wide shared use path, but with a proper surface. It bypasses Honingham entirely and doesn’t really going anywhere terribly useful. Long distance cycle commuters won’t want to use such a narrow path and will probably ride in the road here. It’s possible that the traffic levels on this section of the old A47 will be low, but what traffic there is will probably travel fast.

The Hall Farm underpass and route to Honingham from the west

Just west of Honingham, we come to another underpass of the new road, which is intended as a farm access to Hall Farm, but with a cycle track alongside. We’ll return to this shortly.

If instead of going under the underpass you carry on along the old Dereham Road (after crossing the entrance to the underpass) the cycle track becomes 3m wide and then crosses over the old A47 at an uncontrolled crossing before continuing, turning left to run along a new section of road connecting to the old Dereham Road west of Honingham, heading back into the village. The cycle track ends where the new road meets the old. It has a link to the now truncated Berry Lane, a 2m wide shared use path with a crushed stone surface.

The Wood Lane junction

Returning to the Hall Farm underpass and following the cycle track through it, the width of the cycle track through the tunnel isn’t stated but will have a hard surface. On the other side we turn left and head towards the Wood Lane junction on a 3m wide crushed stone surface path. There are a lot of changes here and some uncertainty as to what the plan actually is.

The Wood Lane junctiom

The massive Wood Lane junction

The area around the present junction of Wood Lane (B1135) is to change utterly to become the site of a large grade-separated junction, designed to accommodate the Norwich Western Link (NWL), which is now cancelled and isn’t going to be built. Wood Lane will remain the main route across the Wensum valley to the A1067 (the Fakenham to Norwich road).

The Wood Lane junction, showing the NWL stubs from the northern roundabout – Image SWECO

The Wood Lane junction will be a massive junction, with giant roundabouts designed to deal with large amounts of traffic. Two stubs are shown on the main drawing and the image above, which were intended as the start of the dual carriageway NWL. These stubs are not shown on detailed engineering drawings and are unlikely to be built.

From the Hall Farm underpass we follow the path that was originally intended to run north along the side of the NWL for some distance. Clearly this isn’t going to happen now the NWL is cancelled. On the large scale drawing, it shows the cycle track looping around the NWL stubs and reaching Wood Lane, but on the more detailed drawings, it simply stops at a farm track with no connection to Wood Lane.

On Wood Lane, at a point opposite where the path from the Hall Farm track might end, a further length of cycle track, again just 2m wide but with a hard surface, runs to the junction where it follows a section of new build road west, which it follows to the point it meets the old A47, where the path ends.

Further west still there is a short section of cycle track (again just 2m wide) along the re-aligned Mattishall Lane west of Hockering, which doesn’t connect to anything. Beyond that is another 2m wide shared use path from the old road out of Hockering, connecting to the existing track to Lyng Road.

Conclusion

This could have been such a useful cycle route had just a little thought gone into its design. Building the new path will open up a long distance cycle route at least as far as the village of Hockering, and via the now bypassed road from Dereham via North Tuddenham. It still offers that potential, but misses out on so much more by being built to such a low standard, and so will not appeal to long distance cyclists nor will it provide a proper connection to Honingham and the Food Enterprise Park.

Cycle routes are not like car routes. Major roads bypass places where people live, a cycle route should go through them. They should also connect to destinations on the way, such as places of employment. This new route could easily have done both. Perhaps most importantly, they should be designed like small roads, as a serious means of travelling.

Amazingly, because the A47 is a trunk road, this is a central government scheme, not Norfolk County Council. we should really expect a lot better from them.

The project information site from SWECO is here

__________________________________________________

Keep up to date with the campaign by subscribing to our free monthly newsletter.


Leave a Reply

Please note all comments will be held for moderation due to the requirements of the Online Safety Act 2023. We'll get to them as soon as possible

Your email address will not be published. Required fields are marked *