The convoluted development of cycle routes at Longwater involved Norfolk County Council seeking advice, ignoring that advice, putting effort into an ill-thought-through scheme instead, while accidentally building something almost quite good but which can’t be connected together. Derek Williams explains

The A47 junction at Longwater has been a barrier to cycling and walking since the southern bypass was built in the early 1990s, and the lack of a safe pedestrian and cycle route across it has been an issue since that time. When William Frost Way was built this only made things worse. All this is described at length in our micro site Crossing the Longwater junction, but for now, a quick summary.
William Frost Way created
In the late 1990s the dual carriageway of William Frost Way seemed massively over-engineered given there was hardly any traffic. By 2014 a shared use cycle path had been built along Dereham Road from Longwater Lane and over William Frost Way to the shops.

Back then there was only Sainsbury’s and a half empty retail park, with a small amount of industry down in the valley, but as we entered the 2000s the shop units filled up and the industrial sites expanded. By the 2010s the traffic problems were getting serious and with many new developments planned gridlock was certain. Something had to be done, so a report was called for.
What follows is a description of how the cycle route plans evolved.
2014 – The Mott MacDonald report

Norfolk County Council (NCC) commissioned a study by Mott MacDonald to identify solutions, and they issued their final report in May of 2014 entitled Longwater and Easton Transport Strategy (PDF download).
The report identified two potential cycle route schemes:
1) Easton College to Long Lane Pedestrian/Cycle Link running south of Showground, crossing A47 into Long Lane.
This was rejected and it was recommended that no further assessment was done: “Expensive new bridge, limited demand, remote pedestrian route.”
2) A pedestrian/cycle bridge over the A47 linking Easton with the Longwater Retail Park.
This was recommended: “A good ped/cycle route between Easton and Longwater is essential, may not be achievable as part of junction scheme.“
2014: Festival Park planning application
Later in 2014 a planning application was submitted to South Norfolk District Council for Festival Park – a huge new housing estate in Easton to the west of the A47 junction.
2015: Requirement for a cycle route
NCC, as the highway authority, stipulated that the developers, Persimmon Homes, were to build a 3m wide cycle route from Festival Park along Dereham Road and over the A47 junction to connect with the existing cycle route on Dereham Road to the east. This had two specific functions: to allow residents to cycle to the Longwater shops, and for their children to walk and cycle to the Ormiston Victory Academy school, both of which involve getting across the A47 junction. This would seem to be the recommended option from the Mott McDonald report.

2016: Planning consent granted
In November the planning consent for Festival Park was granted, which included the cycle route, although the phrase was “across the A47 junction”: the need for a separate bridge was not specified. This is outlined in our blog: The 2014 plans
At some point it became apparent to NCC that it wouldn’t actually be possible to put a 3m wide shared use path over the A47 bridge because it was too narrow. As the Mott MacDonald report made clear, a separate bridge would be needed.
2019: Green Pedalway extension
The Pedalways are a network of mostly low traffic streets and off-road shared use pavements in Norwich which were constructed between 2013 and 2019. The Green Pedalway connects the city centre with Bowthorpe.
NCC put in a bid to the government’s Transforming Cities Fund to extend the Green Pedalway across the A47. This was an entirely different route which made no use of the existing cycle track along Dereham Road. This would seem to be the rejected option from the Mott MacDonald report, a route already dismissed in the report: “Expensive new bridge, limited demand, remote pedestrian route.”
The route was to run from Bowthorpe, along Long Lane, which was severed by the A47 and is now a disused country lane, and then by way of a new bridge over the A47 to the Costessey Park and Ride and then further along Dereham Road to the village of Easton. It would take over some of the existing cycle tracks in Bowthorpe and follow the same route from the Showground to Easton as the Festival Park route. The most notable feature would be a new bridge over the A47 near the Park and Ride.
This proposal made very little sense, either financially or in terms of usefulness.

The Green Pedalway extension didn’t get Transforming Cities funding and wasn’t included in the revised bid submitted in 2020. However, the idea wasn’t dead.
2021: Cycle route from Easton to the Showground announced
In 2021 plans were announced for a shared use path from Festival Park along Dereham Road to the point where it crosses over the road opposite the Premier Inn hotel, just prior to the A47 junction crossing. The rest of the route over the A47, we were told, was to be delivered as part of a separate scheme.
2021: The “future of the Pedalways” consultation
In 2021 NCC announced a consultation on proposed enhancements to the Pedalways network which resulted in the publication of a Local Cycling and Walking Infrastructure Plan (LCWIP). This included the Green Pedalway extension but not the Festival Park route over the A47 junction.
2022: The A47 junction scheme announced
In 2022 the council’s design agency, WSP, produced the inadequate plan we have today for the A47 crossing, it only included a footpath over the junction with no provision for cycling. We describe it in our blog: Dangerous plans for Longwater that ignore cycling

An expensive new bridge was needed at Longwater, but instead of looking for funding to build it NCC promoted the Green Pedalway extension, which avoided the A47 junction and didn’t connect to important destinations, while also needing an expensive new bridge. It also fails to fulfil the planning requirement for Festival Park.
There is already – with no formal crossing in place – demand for the route across the A47 junction. That will only increase once an official link is in place. In planning terms, this crossing is the “desire line”, it’s the way people will go.
2014 – 2025: Massive projects take place along Dereham Road

While all this was happening, major plans unfolded along Dereham Road between Longwater Lane and Bowthorpe. Road upgrades were made as a series of separate projects, specifically the addition of a roundabout bypass from William Frost Way onto Dereham Road, rebuilding of Dereham Road between Longwater and Longwater Lane and a bus improvement scheme between Longwater Lane and Bowthorpe. All of this included either replacing the existing cycle track or creating a new one.
2025: The cycle route along Dereham Road
The result of all these road building projects is a continuous cycle track of reasonable quality from the Green Pedalway at Bowthorpe all the way to Longwater. The route from Easton to the Showground was also built in 2025, so this is what we have now.

As of February 2026 the A47 crossing remains unbuilt with no sign of construction starting soon.
2025: A47 crossing plan improvements scrapped
Since the plans for the A47 crossing were announced in 2022 we have worked with NCC to improve the plans, and we thought we had made some progress. The “get off and push” section was to be confined to just the A47 bridge, with the rest of the crossing route widened to allow cycling. However, in 2025 NCC scrapped all those improvements and reverted to the original plan, a decision that also went against the advice of the safety audit. This is all described here: Longwater – backtrack on improvements
2025: William Frost Way crossing

An important component of the Festival Park route is a two-stage toucan (pedestrian and cyclist) crossing on William Frost Way. At the time of writing this is still under construction, with temporary lights having been in place since September last year. The tragicomedy of the events surrounding the construction of this crossing are described in our blog: Just what is going on with the William Frost Way crossing?
2026: We have a problem
This is the situation we now have, with effectively two long distance cycle routes along Dereham Road, one on each side of the A47 junction with no connection between them. It can’t be emphasised enough how dangerous this situation is. If the crossing is built as planned there will remain huge safety issues, as we outlined here: Longwater needs a safe crossing (with video)
Conclusion
Instead of focusing their efforts on building the crossing of the A47 properly, with a separate bridge for pedestrians and cyclists, time, effort and resources were instead wasted on the ill-thought-through “Green Pedalway extension”.
For decades, lax planning has resulted in a traffic nightmare of huge proportions. There is no simple or affordable way out of this mess and the lesson doesn’t seem to have been learned, with yet another major new store (TK Maxx) about to begin construction.
After all this wasted time we understand NCC have now acknowledged that a dedicated cycling and waking bridge over the A47 is required and have commissioned a feasibility study, over a decade after the Mott MacDonald report described such a crossing as “essential”. If these new proposals come to anything, it will still be many more years before there is a safe and convenient cycle route across the A47 junction.